Motiva Enterprises (2719), Convent

Releases of Sulfur Trioxide

LDEQ Accident Number
Accident Date
Point Source(s) Notes Amount of Release
100801

2007-11-06
Steam Boiler EPN 31F-810
Tail Gas Treatment Unit No. 4 Incinerator Stack EPN 78H-101
VPS-2 Atmospheric Tower Feed Heater EPN 83H-101
Cause: The seal on a diesel circulation pump on VPS-2 (a crude distillation unit) failed as a reslut of a suspected bearing problem. This seal failure caused the release of approximately 434 bbls of untreated (sour) diesel, which ignited, resulting in a fire.

Followup: Yes

Notes: Motiva has slowed down production throughout the refinery until investigations are complete. Inspected, repaired, and rebuilt the pump as necessary. W/r/t pump seal failure, rotating equipmt and other personnel will complete the investigation and implement necessary changes to monitoring, inspection, and maintenance procedures
148.0 pounds