Home | Search | Emissions | Pollutants | About the Database |
LDEQ Accident Number Accident Date |
Point Source(s) | Notes | Amount of Release |
96183 2007-05-14 | Unit Stack Sulfur Dioxide Analyzer | Cause: heavy rainfall with extensive lightning; analyzer disabled by lightning strike Followup: No Notes: Letter mentions sulfur dioxide and hydrogen sulfide but does not cite emission of Sulfur Trioxide, which is listed in the attached verabl repor | |
109022 2008-09-13 | B-11 Flare, B-12 Flare, Sulften Stack, C-Cat Scrubber, | Cause: Hurricane Ike Followup: Yes Notes: Power Failure causes release of huge amount of S02. Loss of Pecan Grove substation caused the loss of power to equipment in the SRU, Central Amine, cid Plant, Sour Water Stripper, Unicracker, Wastewater Treating and Coker II Units. Combustion efficiencyof 99% was used to calculate S02 emissions - is that an appropriate figure? Follow-up report on 10/27/2008 discusses emissions from B-11 Flare only REMEDIAL ACTIONS - perform feasability study of reliable power supply for acid block ; Install nsary equipment to start up JC-201 Compressor with less than RQ Flare Emissio |
Connect With Us: