Home | Search | Emissions | Pollutants | About the Database |
Accident # | 142568 |
tate Police # | N/A |
Accident Date | 2012-08-30 |
Report Date | 2012-10-10 |
Follow-up Date | 0000-00-00 |
Follow-up: | No |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Wastewater | 20 h | Outfall 002 | NO | NO | NO | BRQ |
Stormwater | 20 h | Outfall 002 | NO | NO | NO | BRQ |
Accident Classified As: Below Reportable Quantity (BRQ)
Upset conditions which led to a LPDES bypass as a result of Hurricane Isaac and the associated internal facility flooding that occurred as a result.
The bypass consisted of excess stormwater mixed with process wastewater and was made to the LPDES permitted stormwater pond which discharged via Outfall 002 to the Ascension Ditch, to the St. James Canal, and then to the Blind River. The stormwater drainage system was still compromised by flooding conditions and Outfall 002 continued to discharge until 09/01/2012 at 8:30pm. They mention that complete details are provided in a written report submitted on 09/07/2012 but we were unable to find this report. The facility claims that all permit required analytical information for Outfall 002 were within permit limits in august and september. The results show that the bypass didn't cause a water quality violation, exceed any reportable quantity, or exceed any permit limit.
Connect With Us: