Accident # | 83968 |
tate Police # | N/A |
Accident Date | 2005-11-12 |
Report Date | 2005-11-18 |
Follow-up Date | 2006-11-07 |
Follow-up: | Yes |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Vinyl Chloride | 19h 28m | Incinerator A (Emission Pt. No. 203) and Incinerator B (Emission Pt. No. 204) | NO | NO | NO | 1.6 pounds |
Accident Classified As: Reportable Quantity
Wastewater pump discharge was intermittently backing into caustic scrubber recirculation lines as a result of differential pressure.
The refinery states that all applicable standard operating procedures were followed.
A skillet blind was inserted in the line near the suspected leaking valve to Incinerator B to protect against potential leak. The applicable pump-down procedure was modified/improved. A check valve was installed in the affected level control blowdown line to prevent liquid backup. The refinery submitted and received a revised permit for the affected sources, which it says better accounts for hourly maximum emission rates, on August 11, 2006. LABB's file only contains the letter dated 11/7/2006 and no LDEQ report, SPOC report, etc.