Accident # | 158573 |
tate Police # | N/A |
Accident Date | 2014-09-08 |
Report Date | 2014-10-10 |
Follow-up Date | 0000-00-00 |
Follow-up: | No |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Accident Classified As: No Information Given
According to the e-mail from Mr. Stubbe (Manager Environmental Engineering), the project and turnaround activities that commenced in late July continue. No Reportable Quantities (RQ) were exceeded, no emergency condition existed, and no odor complaints were received from inside or outside the plant. DEQ inspectors conducted a survey of the area on 9/16/14 and 9/24/14. The first survey found no odors in the area during surveillance, the second survey conducted found some odors in the neighborhood located on the north side of the facility. *Starting 7/28/14, the refinery executed a planned shutdown of several process units for project work and scheduled maintenance. Affected units include the Hydrocracker, the FCCU, the Alkylation Unit and the ROSE unit.
Related to incidents #158394, 158330, 158905, 158516, 158452.