Accident # | 130645 |
State Police # | 11-02114 |
Accident Date | 2011-04-13 |
Report Date | 2011-04-19 |
Follow-up Date | 0000-00-00 |
Follow-up: | No |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Propylene | 3m | RT-03 | NO | NO | YES | 4,619.0 pounds |
Ethylene | 3m | RT-03 | NO | NO | YES | 3,414.0 pounds |
Flammable Vapor | 3m | RT-03 | NO | NO | YES | 19,903.0 pounds |
Accident Classified As: Reportable Quantity
The South Ethylene Purification Unit (EPLA-S) experienced operational difficulties from depropanizer tower RT-03. RT-03 experienced operational difficulties with its overhead condensers when a control valve failed, resulting in EPLA-S receiving unsteady feed rates and material molecular weights. Due to teh unsteady feed, material was routed from EPLA-S to the flare system and an atmospheric safety valve released material. A control valve failed.
Caused by unanticipated control valve failure.
Material was routed from EPLA-S to the flare system. To end the release, rates at RT-03 and EPLA-S were reduced. The failed control valve has been isolated. It will be repaired prior to being returned to service.