Accident # | 130330 |
State Police # | 11-01830 |
Accident Date | 2011-03-31 |
Report Date | 2011-04-07 |
Follow-up Date | 2011-05-05 |
Follow-up: | Yes |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Hydrogen Sulfide | 2m | Coker Blowdown Vent | NO | NO | NO | BRQ |
Volatile Organic Compounds (VOCs) | 2m | Coker Blowdown Vent | NO | NO | YES | 13.9 pounds |
Carbon Monoxide | 2m | Coker Blowdown Vent | NO | YES | NO | 1.3 pounds |
1,3-Butadiene | 2m | Coker Blowdown Vent | NO | NO | YES | BRQ |
Accident Classified As: Below Reportable Quantity (BRQ)
The facility reported the Coker unit was water quenching the coke material in Cooke Drum PV-918 and encountered a problem with an automated water quench sequence.
The facility took the problematic water quench sequence out of automatic mode and and manually closed off on the water control valve. Once the pressure was reduced to normal operation, the quench cycle was completed. The sequence has been adjusted, and additional orders have been given to the Coker operators so that this activity is consistent on each work shift.