Home | Search | Emissions | Pollutants | About the Database |
Accident # | 130697 |
State Police # | 11-02231 |
Accident Date | 2011-04-18 |
Report Date | 2011-04-25 |
Follow-up Date | 0000-00-00 |
Follow-up: | No |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Sulfur Dioxide | 15m | Fluid Catalytic Cracker (FCC) Unit | NO | YES | NO | 187.0 pounds |
Accident Classified As:
According to LDEQ, there was "a pump shut down due to a power trip. After thepump shut down, pressure levels built in the absorber column," which resulted in a release of sulfur dioxide.
BRQ According to LDEQ, "There is a back-up pump in case of emergency where flow was restored during the... flaring." No further information given.