Accident # | No LDEQ Number Available |
tate Police # | N/A |
Accident Date | 2007-02-27 |
Report Date | 2007-03-01 |
Follow-up Date | 2007-03-07 |
Follow-up: | Yes |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Benzene | 11h | Marine Dock 1 | NO | NO | YES | 0.1 pounds |
Highly Reactive Volatile Organic Compounds (HRVOCs) | 11h | Marine Dock 1 | NO | NO | NO | 4.0 pounds |
Volatile Organic Compounds (VOCs) | 11h | Marine Dock 1 | NO | NO | YES | 439.8 pounds |
Compressed Flammable Gas | 11h | Marine Dock 1 | NO | NO | YES | 2,036.4 pounds |
Accident Classified As:
The piping on a newly installed liquid separation vessel was incorrectly piped
Root Cause Analysis is being performed. DEQ Field Interview Report states that the facility failed to have control device in place to ensure that the newly installed piping was correctly piped prior to loading.