Accident # | 112389 |
State Police # | 09-0304 |
Accident Date | 2009-01-29 |
Report Date | 2009-02-26 |
Follow-up Date | 0000-00-00 |
Follow-up: | No |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Carbonyl Sulfide | 1 hour | B-Topper unit | NO | NO | YES | 162.9 pounds |
Carbonyl Sulfide | 1 hour | B-Topper unit | NO | NO | YES | 162.9 pounds |
Carbonyl Sulfide | 2 hours | B-Topper unit | NO | NO | YES | 244.8 pounds |
Hydrogen Sulfide | 1 hour | B-Topper unit | NO | NO | NO | 3.1 pounds |
Hydrogen Sulfide | 2 hours | B-Topper unit | NO | NO | NO | 4.7 pounds |
Accident Classified As:
B-Topper unit shut down, flaring of hydrocarbons and smoking furnaces as a result of the failure of a 13.8kV underground feeder cable.
Cable installed underground. No advance knowledge of failure available.
Release of carbonyl sulfide occurred on 01-29-09, 01-30-09, 02-05-09. Release of hydrogen sulfide occurred on 01-30-09, 02-05-09.Efforts were made to shut down the B-Topper unit and affected electrical equipment was tripped off.