Home | Search | Emissions | Pollutants | About the Database |
Accident # | 94158 |
State Police # | 06-00901 |
Accident Date | 2007-02-23 |
Report Date | 2007-03-01 |
Follow-up Date | 0000-00-00 |
Follow-up: | No Information Provided |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Sulfur Dioxide | 3h 15m | FLARE-Temperature Transmitter / | NO | YES | NO | 367.0 pounds |
Accident Classified As:
the startup followed a shutdown of the #3 SRU complex on 2/23/2007, after its source of acid gas, the Hydrocracker Unit, experienced an automatic safety shutdown . The shutdown was triggered by a high temp. indication on the HCU Makeup Gas Compressor. Atemp. transmitter failed due to damage to its insulation and a loose connection. In failing, the transmitter sent a false high temp. indication, which triggered the shutdown of the compresso
This incident was not preventable because the failure of the wiring was not a predictable event. Additionally, the excess emissions are a normal part of the unit startup. Remedial Measures - MOUSA reprogrammed the transmitter to send a low temp. signal on failure, which will avoid a compressor shutdown. MOUSA activated the instrument's dual element technology, such that if one element fails, it will automatically switch to the backup. This will improve the reliability of the transmitter. Nthe shutdown was triggered by a high temp. indication on the HCU Makeup Gas Compressor A. A temp. transmitter failed due to damage to its insulation and a loose connection. In failing, the transmitter sent a false high temp. indication, which trigge