Accident # | 91657 |
State Police # | 06-06664 |
Accident Date | 2006-10-26 |
Report Date | 2006-11-02 |
Follow-up Date | 2006-12-14 |
Follow-up: | Yes |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
1,3-Butadiene | No information given | NO | NO | YES | 4.9 |
Accident Classified As: Below Reportable Quantity (BRQ)
Operators discovered a pin hole leak in a finishing butadiene line while conducting air monitoring.
No information given
Upon discovery, a temporary clamp was installed and an order was placed for a permanent clamp. Once permanent clamp was fabricated and delivered, it was installed over the leak.