Home | Search | Emissions | Pollutants | About the Database |
Accident # | 83055 |
State Police # | No Information Given |
Accident Date | 2005-10-13 |
Report Date | 2005-10-20 |
Follow-up Date | 0000-00-00 |
Follow-up: | No |
Pollutant | Duration | Point Source | Greenhouse Gas | Criteria Pollutant | Ozone forming chemical | Amount of Release |
Benzene | No information given | Catalytic Reformer #1 Unit | NO | NO | YES |
Accident Classified As: No Information Given
During excavation activities with the construction of a new flare knockout pot at the CR-1 unit, liquid hydrocarbons were observed seeping into the excavation.
The area in question was previously investigated and it was determined that there was a single concentration of Benzene that exceeded the RECAP screening standard but fell below the MO-1 standard; there was a conference on 10 18 05 between Oliver Boyd and someone from the LDEQ division and it was agreed that since the area was being managed under the approved east site groundwater management program, no further assessment or action is warranted.
Connect With Us: